Expand mobile version menu
  Skip to main content

Construction Manager

salary graphic

AVG. SALARY

$99,910

education graphic

EDUCATION

Bachelor's degree or higher +

job outlook graphic

JOB OUTLOOK

Stable

Real-Life Activities

Real-Life Math

You are a construction manager. You have just won a bid to renovate an office building.

Now the real work begins. There are several steps to renovating a building, from demolishing walls to installing electrical equipment.

In order to not go over budget, you need to complete the project in the least amount of time possible. In order to accomplish this, you rely on a tool called critical path management (CPM).

A critical path is a drawing outlining the order in which each phase of the project must be completed in order for the entire project to be completed in the least amount of time. Some jobs must be completed before another job can be started, while some jobs can be worked on at the same time. A critical path helps organize the project.

To create a critical path, you begin by writing down all the jobs that must be completed and the estimated time each job will take. You also assign a letter to each job.

A = Finalize blueprints = 2 weeks
B = Demolish unneeded old walls = 3 weeks
C = Finalize contracts with subcontractors = 2 weeks
D = Frame new walls = 4 weeks
E = Install heating, ventilation and air conditioning = 1 week
(This would include things like putting in heat registers and air ducts)
F = Install plumbing where needed = 3 weeks
G = Install electrical wiring in the walls, such as electrical switches and plug-ins = 5 weeks
H = Finish the walls by putting plaster over them = 2 weeks

If you waited to complete each job before starting another one, the project would take a total of 22 weeks to complete:

2 + 3 + 2 + 4 + 1 + 3 + 5 + 2 = 22

That is too long. But you can't just start ordering carpenters, electricians and laborers to begin working all at once. There are certain restrictions.

For example, the blueprints must be completed before any other work can begin. The old walls must be demolished before the new walls can be framed. Framing must be finished before you can start installing heat ducts or electrical wiring. And all the other work must be completed before you begin plastering the walls.

But, for example, E and F can be completed at the same time as G, and in a shorter time. That means you only need to account for enough time to finish G -- you don't need to add extra time for E and F.

How can you organize the order of the work in such a way that the project will be completed in as short a period of time as possible?

Contact

  • Email Support

  • 1-800-GO-TO-XAP (1-800-468-6927)
    From outside the U.S., please call +1 (424) 750-3900

Support


Powered by XAP

OCAP believes that financial literacy and understanding the financial aid process are critical aspects of college planning and student success. OCAP staff who work with students, parents, educators and community partners in the areas of personal finance education, state and federal financial aid, and student loan management do not provide financial, investment, legal, and/or tax advice. This website and all information provided is for general educational purposes only, and is not intended to be construed as financial, investment, legal, and/or tax advice.